At Work | 2024
Summary of maintenance and special projects completed in 2024.
Summary of maintenance and special projects completed in 2024.
Each year we maintain the 33 miles of channels and banks to ensure the watershed's maximum capacity.
Each year we mow and inspect all the dams, repair damaged, failing or compromised dam components.
Restoration of the Styx River bank and replacement of a 42' long pipe and culvert.
This structure had deteriorated over the past 50 years and was beginning to fail impacting the river bank and maintenance berm along the River Styx Channel.