Projects 2017
Dam III-A Drainage

ODNR - Dam Safety directed Chippewa Subdistrict to address a wet area at the outside toe of the dam. It was determined that a drain tile would be adequate to dry out this low area. 1670 feet of 6-inch drain tile was installed. 760 feet of old fencing was removed to facilitate the project and will be replaced with maintenance-friendly high-tensile fence.

 

Above: Chippewa Dam III-A